What cable does an EV charger need in Pakistan?

PILONE CABLES TECHNICAL TEAM · UPDATED 21 SEPTEMBER 2026

Work from the charger's current, not its kilowatts — and treat it as a load that runs at full current for hours.

A 7 kW single-phase charger draws 7000 ÷ 220 = 31.8 A. An 11 kW three-phase charger draws 11000 ÷ (1.732 × 400) = 15.9 A in each phase. That current is the starting point; the conductor size then depends on how the cable is installed, how hot it gets, how many circuits it is bundled with, and how far the charger sits from the board. There is no single answer to “what size cable for a 7 kW charger”, and anyone who gives you one without asking those questions is guessing. What this page gives you is the arithmetic and the variables, so the electrician who signs off the job is checking a number rather than inventing one.

Start from the charger's current, not its kilowatts

Kilowatts sell chargers; amps size cables. The conversion is one line, and it is worth doing yourself because the same kilowatt figure means completely different currents on a single-phase and a three-phase supply. An 11 kW three-phase charger pulls less current per conductor than a 7 kW single-phase one, which surprises people who assume the bigger number needs the bigger cable.

Charger current derived from the rating: single phase is kW x 1000 / 220, three phase is kW x 1000 / (1.732 x 400). Real chargers are sold by their current setting as often as their kilowatts, and the rating plate is the authority. Figures rounded to one decimal.
ChargerSupplyCurrent drawnArithmetic
3.6 kWSingle phase 220 V16.4 A3600 ÷ 220
7 kWSingle phase 220 V31.8 A7000 ÷ 220
11 kWThree phase 400 V15.9 A per phase11000 ÷ (1.732 × 400)
22 kWThree phase 400 V31.8 A per phase22000 ÷ (1.732 × 400)

Most homes in Pakistan are on a single-phase 220 V connection, which caps a home charger at around 7 kW in practice. Three-phase is common in larger houses, plazas and anywhere with a commercial connection, and it is what makes 11 kW and 22 kW units possible. Check which you have before you choose a charger, not after — it is the single biggest constraint on the decision, and it is covered on what your supply needs before a charger.

Why an EV charger is not like the rest of the house

Almost nothing else in a house behaves like a car charger. A geyser heats up and cuts out on its thermostat. An air conditioner cycles. A kettle runs for three minutes. A charger draws close to its full rated current continuously for four, six, sometimes ten hours, usually overnight when nobody is watching it and often in the hottest part of the year.

That matters because the tabulated current capacity of a cable assumes it can lose heat to its surroundings. A cable that never reaches steady state on a kettle circuit reaches it comfortably on a charger circuit. The result is that the derating factors most domestic wiring quietly gets away with ignoring — conduit, bunching, a hot roof void, a June afternoon in Lahore — are the factors that actually decide an EV circuit.

Hours, not minutes

A charging session holds near-full current long enough for the cable, the conduit and the air around them to reach their final temperature.

Usually unattended

Overnight charging means nobody notices a warm cable, a loose terminal or a cover that was never screwed back on.

Often the biggest load

On a single-phase domestic supply a 7 kW charger can be the largest single load in the house by some margin.

Which cable sizes carry those currents

The table below is the tabulated starting point: what each size carries clipped direct in open air at 30°C. Read it as the best case. Every real installation takes something off these numbers, and on an EV circuit it takes more off than usual, for the reasons above.

Copper conductor, class 2. Current capacity and voltage drop per BS 7671, installation reference method C (clipped direct), 30°C ambient; conductor resistance and stranding per IEC 60228. Two loaded conductors is a single-phase circuit, three loaded is a three-phase one. These are tabulated figures before any correction for installation method, ambient temperature or grouping — they are a starting point for a calculation, not a cable recommendation.
SizeStrands (class 2)2 loaded3 loadedVoltage dropCopper per core
2.5 mm²7/0.6727 A24 A18 mV/A/m22.2 kg/km
4 mm²7/0.8536 A32 A11 mV/A/m35.6 kg/km
6 mm²7/1.0446 A41 A7.3 mV/A/m53.3 kg/km
10 mm²7/1.3563 A57 A4.4 mV/A/m88.9 kg/km
16 mm²7/1.7085 A76 A2.8 mV/A/m142.2 kg/km

Put the 31.8 A of a 7 kW single-phase charger against that table and you can see why the answer is not obvious. 4 mm² carries 36 A on paper, which clears 31.8 A with very little margin — and margin is exactly what a continuous load in a hot conduit spends. 6 mm² at 46 A leaves room for the correction factors to take their bite. Which one is correct for your installation depends on the route, and that is a calculation, not a preference.

These are tabulated figures before derating. Current capacity depends on how the cable is installed, the ambient temperature and how many circuits share the route, and an EV charger loads a cable harder and for longer than most domestic circuits. Work your own case through the cable size calculator and the voltage drop calculator, follow the charger manufacturer's own installation instructions, and have a licensed electrician confirm the conductor size, the protective device and the earthing arrangement before anything is energised.

The three things that move the answer

Given the same charger and the same cable, these three change the size that is actually correct. None of them is optional, and all three tend to point the same way — upward.

How it is installed

Clipped to a wall in open air is the friendly case. Buried in a conduit, in a wall chase, or in insulation, the same cable sheds heat far more slowly and carries less.

How hot it gets

The tables assume 30 degrees C. A Lahore roof void or an outside wall in June is well above that, and the correction is applied before the cable is chosen, not after.

What it runs with

A cable bundled with other loaded circuits is warmed by them. Grouping factors apply to the whole bunch, not just to the newest cable in it.

Then there is distance, which is a separate question with its own arithmetic: a cable can be comfortably large enough to carry the current and still drop too many volts over a long run. That is worked through on charger far from the board.

The rest of the circuit

The cable is one part. An EV charge point is a dedicated circuit and needs the rest of it to match: its own way on the distribution board rather than a spur off something else, a protective device rated so the cable is protected, and an earthing arrangement the charger will accept. Many units also specify the type of residual current protection they need, because of the kind of fault current a vehicle charger can produce.

We are not going to tell you which device to fit. The charger manufacturer publishes what its unit requires, and those instructions carry more authority than any general guide — including this one. Take them to your electrician along with the cable calculation, and let the two be checked against each other. What we can tell you about is the copper: see 6mm cable, 4mm cable, and the cable price list for what the sizes cost at the factory rate.

Frequently asked

What size cable do I need for a 7kW EV charger?
A 7 kW single-phase charger draws 7000 / 220 = 31.8 A, so the cable has to carry at least that after derating. 4 mm2 carries 36 A and 6 mm2 carries 46 A clipped direct at 30 C, but the correct size depends on how the cable is installed, how hot the route gets, whether it is bundled with other circuits and how far the charger is from the board. A continuous load like a charger spends the margin that a normal domestic circuit keeps. Have a licensed electrician confirm the size for your installation.
How many amps does an EV charger draw in Pakistan?
Divide the rating by the supply voltage. On a single-phase 220 V connection, a 3.6 kW charger draws 16.4 A and a 7 kW charger draws 31.8 A. On a three-phase 400 V supply, an 11 kW charger draws 15.9 A per phase and a 22 kW charger draws 31.8 A per phase. The rating plate on the unit is the authority, since many chargers are sold by their current setting rather than their kilowatts.
Can I run an EV charger on my existing house wiring?
No. A charge point is a dedicated circuit run from the distribution board, not a socket spur. An EV charger draws near its full current for hours at a time, which is a different duty from anything else in a house, and existing socket circuits are neither sized nor protected for it. Whether your supply can take the extra load at all is the first question to answer.
Is 2.5mm cable enough for a car charger?
2.5 mm2 carries 27 A clipped direct at 30 C, which is below the 31.8 A a 7 kW single-phase charger draws before any derating is applied. It may suit a small 3.6 kW unit drawing 16.4 A on a short, well-ventilated run, but that is a calculation for the specific installation rather than a general answer. Size the circuit from the charger current, the installation method and the run length.
Does an 11kW charger need a bigger cable than a 7kW one?
Not necessarily, because the two are usually on different supplies. An 11 kW three-phase charger draws 15.9 A in each phase, which is less per conductor than the 31.8 A a 7 kW single-phase charger draws. The three-phase unit needs more conductors, not thicker ones. This is the most common mistake people make reading charger specifications.