Skip to content
Factory-direct from Lahore · Nationwide delivery in 2–4 days +92 319 4262451 WhatsApp

Cable for a data center: rack, PDU and backbone feeds

PILONE CABLES TECHNICAL TEAM

A server room is the one building load with no diversity in it. The racks pull what they pull at three in the morning as hard as at noon, and the cable never gets a cool hour. That is what changes the sizing, and it is what this page works through.

Size every circuit on 100% of its rated load, then derate it for the bundle it runs in.

A 5 kW rack on a single-phase 220 V feed draws 5000 ÷ 220 = 22.7 A and holds it, so it belongs on a 32 A breaker. 4 mm² copper is rated 36 A clipped direct at 30 °C, but a dozen circuits bunched in one under-floor basket pull that below the breaker rating — 6 mm² at 46 A is the size that still clears it. Where a rack has an A feed and a B feed, each one has to carry the whole rack alone, so both are sized for the full 22.7 A.

What a rack works out to in amps

Start from the rack's rated feed, not from what the servers currently idle at. Divide by 220 V for a single-phase feed, take the breaker at 125% of that current, and read the base cable size off the same row. The 125% is what makes a rack different from a house circuit: the load is continuous, so the protective device is not sized on the bare figure.

Single-phase rack feeds at 220 V. Current = rack rating ÷ 220; breaker at 125% of the current, taken up to the next standard rating. Current capacity is for two loaded conductors, copper, PVC, per BS 7671 reference method C (clipped direct), 30 °C ambient; conductor data per IEC 60228. This is the base figure before grouping and ambient derating — the worked example below shows what that step costs. Verify sizing with a licensed electrician for your installation.
Rack feedCurrent at 220 VBreakerBase sizeBase capacity
2 kW9.1 A16 A2.5 mm²27 A
3 kW13.6 A20 A2.5 mm²27 A
5 kW22.7 A32 A4 mm²36 A
7 kW31.8 A40 A6 mm²46 A
10 kW45.5 A63 A10 mm²63 A

The 10 kW row is the one people get wrong. The base read-off is 10 mm² at 63 A — exactly the breaker, with no margin left to spend on grouping. Under a floor with other circuits it will not hold, so the size we would actually run is 16 mm² at 85 A. That is a judgement on top of the table, not a reading of it. A three-phase PDU feed changes the arithmetic to line current at 400 V — that ladder lives on 3-phase cable size.

A 5 kW rack, A and B feeds, under a raised floor

The rack is rated 5 kW, the feeds run 25 m from the panel, and both of them share a floor basket with ten other circuits in a room held warm by the racks themselves.

So the feed is 6mm 2 core cable, twice, on separate routes. Split A and B into different baskets and each group gets smaller, which is worth more than a size of copper. Check your own run in the voltage drop calculator.

Every capacity on this page is a 30 °C clipped-direct figure. A data hall runs warm, circuits run bunched, and both correction factors bite at once — take them from BS 7671 for your actual arrangement. Have a licensed electrician confirm sizes against the load schedule before you order.

Cable for the power side of the room

Where a feed leaves the room — out to a generator, across a yard, under a slab — the mechanical protection matters more than the flex, and that run goes in 16mm armoured cable or the size the load calls for. What to check before burying it is on underground cable.

What we make, and what a data hall spec often asks for

Two honest limits, stated before you order rather than after. First, "data center cable" means two different things: the Cat6 and fibre between switches and servers, which we do not make, and the power cable behind it, which we do. Second, our line is PVC insulated copper and aluminium at a 70 °C conductor rating, 450/750 V fixed and 300/500 V flexible. If your specification calls for low-smoke or fire-survival cable on the critical circuits, that is a separate certified product class — read our position on fire resistant cable and tell us the requirement before you buy, not after.

Sending a load schedule or a BOQ

Send the lines

Size, cores, construction and metres per line — or the load schedule and we will read the sizes off it with you.

Get today's rate

Cable is priced off the day's copper rate, so the quote is dated. No dealer margin between the line that drew it and you.

Collect or dispatch

Collect from the Lahore factory, or we dispatch by courier or transport — Punjab in 1–2 days, rest of Pakistan in 2–4.

Questions data center buyers ask

What cable is best for a data center?
Two different cables get called that. The data cable between switches and servers is Cat6 or fibre, and we do not make it. The power cable behind it — the run to the PDU, the rack feed, the backbone between panels — is ordinary copper, sized on the connected load and the way it is grouped. That second one is what we draw in Lahore and what this page sizes.
How many amps does a 5 kW rack draw at 220 V?
5000 W ÷ 220 V = 22.7 A, and unlike a house circuit it holds that figure all day. Size the cable on the full 22.7 A with no diversity allowance, put it on a 32 A breaker, and then apply the grouping and ambient correction for the basket or tray the cable actually runs in.
Do the A and B feeds each need full-size cable?
Yes. The point of a dual path is that either side can carry the rack alone when the other is down or being worked on. Sizing each feed for half the load defeats it. Both feeds get the same size, and both count toward the grouping factor if they share a route — which is one reason A and B are usually run in separate baskets.
Is PVC cable acceptable in a data hall?
That is a question for the project specification, not for us. Our line is PVC insulated copper and aluminium, 70 °C conductor rating, 450/750 V. Many data hall specifications call for low-smoke or fire-survival cable on some circuits, which is a different product class with its own certification. Read our honest position on the fire resistant cable page before you order.
Can you quote a data center project from our BOQ?
Send the line items — size, cores, construction and metres — on WhatsApp and you get the day's factory rate against each line. Cable is priced off the daily copper rate, so a quotation is dated rather than open-ended. Punjab in 1–2 days, rest of Pakistan in 2–4.

Cable for the server room, at the factory rate

Send the load schedule or the cable lines from your BOQ. You get the day's factory price against each one, with dispatch by courier or transport.

WhatsApp for a quote