Skip to content
Factory-direct from Lahore · Nationwide delivery in 2–4 days +92 319 4262451 WhatsApp

Voltage drop: find where the volts are going

PILONE CABLES TECHNICAL TEAM

Measure at the main board and at the load while the heavy appliance is running: low at both means the supply, normal at the board and low at the load means your cable, and the difference is the drop.

Where it is the cable, the fix is a larger conductor on that run — and the length sets the size, not the current. 2.5 mm² carries 27 A comfortably, but at 20 A over a 30 m run it loses 10.8 V, which is 4.9% of 220 V and outside a 3% budget. Work your own numbers in the voltage drop calculator, or read the tables below.

Is it your cable, or is it the supply?

Every voltage-drop guide written for a stable grid skips this step, and in Pakistan it is the first one. The feeder in the street sags at peak hours whatever you do inside the house, so before anyone buys copper, find out which of the two is losing the volts.

Take two readings at the same moment, with the pump or the AC actually running: one at the main distribution board, one at the appliance terminals. If the board reads 190 V and the appliance reads 188 V, the supply is down and your cable is losing 2 V — a thicker cable buys you those 2 V and nothing else. If the board reads 218 V and the appliance reads 205 V, your own run is losing 13 V, and that is the number a larger conductor removes. Take both readings on the same meter, one after the other, and keep the load constant between them.

The honest conclusion is often the unwelcome one: where the supply itself is low, the answer is a stabiliser or a complaint to the utility, not a bigger coil. We would rather say that than sell the wrong fix.

How much voltage drop is acceptable?

Voltage drop is the voltage a cable loses along its own length: millivolts per amp per metre, multiplied by the current and by the one-way run. The usual design budget is 3% for lighting circuits and 5% for everything else, measured from the origin of the installation to the point of use. On Pakistan's 220 V single-phase supply that is 6.6 V and 11 V.

Two things about that budget catch people out. It covers the whole path, so the submain from the meter to the board has already spent part of it before the final circuit starts — give a final circuit half the allowance and you will not be caught short. And it is a design limit, not a failure threshold: a motor at 5% down is inside the rules and still starting harder than it would at 2%.

Volts lost per amp, per metre

One figure per size does all the work. Multiply it by the current and by the one-way run in metres, then divide by 1,000 to get volts.

Single-phase, two-core figures. Do not reuse this column for a 400 V three-phase run — that has its own values. Voltage drop and current capacity per BS 7671 (IEC 60364-5-52), reference method C (clipped direct), 30 °C ambient, copper, PVC; conductor resistance per IEC 60228. Derate capacity for conduit, bundling and higher ambient. Verify sizing with a licensed electrician for your installation.
SizeVoltage dropCapacity, 2 loaded coresResistance, class 2
1.5 mm²29 mV/A/m19.5 A12.1 Ω/km
2.5 mm²18 mV/A/m27 A7.41 Ω/km
4 mm²11 mV/A/m36 A4.61 Ω/km
6 mm²7.3 mV/A/m46 A3.08 Ω/km
10 mm²4.4 mV/A/m63 A1.83 Ω/km
16 mm²2.8 mV/A/m85 A1.15 Ω/km
25 mm²1.75 mV/A/m112 A0.727 Ω/km
35 mm²1.25 mV/A/m138 A0.524 Ω/km

A three-phase 400 V run works to different figures and a different budget, and reusing this column for it will undersize the cable. That case is on three-phase cable size.

How long a run each size will hold

Turn the sum around and it answers the question people actually have: how far can I go before the size has to change?

One-way run in metres that keeps the drop inside 3% of 220 V (6.6 V), at four common circuit currents. Run = 6,600 ÷ (mV/A/m × amps), rounded down. For a 5% budget (11 V), multiply any figure by 1.67. Dashes mark a current the size cannot carry: 1.5 mm² is rated 19.5 A and 2.5 mm² is rated 27 A on method C at 30 °C, before derating. Verify sizing with a licensed electrician for your installation.
Size10 A16 A20 A32 A
1.5 mm²22 m14 m11 m
2.5 mm²36 m22 m18 m
4 mm²60 m37 m30 m18 m
6 mm²90 m56 m45 m28 m
10 mm²150 m93 m75 m46 m
16 mm²235 m147 m117 m73 m

Measure the run the cable takes, not the distance across the plot: down the wall, along the chase, out through the sleeve and up to the terminal, plus a metre at each end. On a farm or a plot with an outbuilding that route is often twice what people guess.

A worked example: 20 A over 30 metres

A socket submain to an outbuilding, 20 A, 30 m one way, single phase. On paper 2.5 mm² is the obvious choice: it is rated 27 A and the load is 20 A, so it passes on current with 7 A to spare.

Now the length. 18 × 20 × 30 ÷ 1000 = 10.8 V, which is 4.9% of 220 V. It clears the 5% limit by a fifth of a volt and fails a 3% budget outright, and that is before the submain feeding the board has spent anything. Step up to 4 mm²: 11 × 20 × 30 ÷ 1000 = 6.6 V, exactly 3.0% — on the line, not inside it. Step up again to 6 mm²: 7.3 × 20 × 30 ÷ 1000 = 4.38 V, 2.0%, with room for the day the load grows.

That is the whole point of this page. All three sizes carry 20 A without getting hot. Only the last two deliver usable voltage at the far end, and the gap between 4 and 6 mm² on a long run is worked through on 4mm vs 6mm cable.

Why the pump will not start on a long run

A submersible or a booster pump that runs happily once it is going but refuses to start — hums, draws, trips — is the classic long-cable case, and it is arithmetic rather than a fault. Drop scales with current, and a direct-on-line induction motor pulls a multiple of its running current for the instant it breaks away; the figure is on the motor plate, and it is the one to work with, not a rule of thumb. A run losing 5 V while the pump turns can be losing several times that at the instant it tries to start, and the motor never reaches the voltage it needs.

The same mechanism explains lights that dim when the AC compressor or the water motor kicks in. The starting current is shared with everything on that submain for a fraction of a second, and the dip you see is the drop in the cable feeding all of it. If the dimming is confined to one circuit, look at that circuit's size; if the whole house dips, look at the submain from the meter, or at the supply. Pump runs have their own sizing walk-through on cable for a submersible pump.

Will thicker wire fix low voltage in the house?

Only the share your own cable is losing, and that is usually smaller than people hope. Take a 1,800 W load on an 18 m run at a sagging 190 V: the current is 1800 ÷ 190 = 9.5 A, and the cable's own loss is 18 × 9.5 × 18 ÷ 1000 = 3.08 V on 2.5 mm² against 11 × 9.5 × 18 ÷ 1000 = 1.88 V on 4 mm². Going up a size buys back 1.2 V of the 30 V the street has taken away.

So size the cable for the run because the run demands it, not as a defence against a weak feeder. Where the whole street is down, a stabiliser or the utility is the answer. Where your own board reads fine and the far end does not, the copper is the answer — and one size up is usually enough, because the drop falls roughly in step with the increase in conductor area.

A cable that is the right size for current can still be the wrong size for length, and neither number is settled by looking at the wire. Have a licensed electrician confirm the size for your load, your run and your installation method, and take the derating factors for conduit, bundling and ambient above 30 °C from BS 7671. If the cable is also running hot, that is a separate diagnosis — see cable overheating.

Frequently asked

How much voltage drop is acceptable — 3% or 5%?
Both, for different circuits. The usual design budget is 3% for lighting and 5% for everything else, measured from the origin of the installation to the point of use. On a 220 V single-phase supply that is 6.6 V and 11 V. The budget covers the whole path, so a final circuit only gets what the submain has not already spent — give it half and you will not be caught out.
Lights dim when the AC or the motor starts — is that my cable or WAPDA?
Two readings settle it. Measure at the main board and at the load, both while the heavy appliance is running. If both are low together, the supply is sagging and no cable will fix it. If the board reads normal and the load reads low, the difference is the drop in your own cable, and that is the part a larger conductor removes.
Why will my submersible pump not start on a long cable run?
Because the drop scales with current, and starting current on a direct-on-line motor is several times running current — take the figure from the motor plate. A cable that loses 5 V while the pump runs can lose several times that in the instant it tries to start, and the motor never reaches the voltage it needs to break away. It then either hums and trips, or starts only when the neighbours' load is off.
Will thicker wire fix low voltage in my house?
Only the part your own cable is losing. If the meter itself reads 190 V, the feeder in the street is sagging and a thicker cable inside the house buys you back a volt or two at most. Measure at the meter first. Where the supply is the problem the answer is a stabiliser or a complaint to the utility, not a bigger coil — we would rather say so than sell you the wrong fix.
How long a run can I do on 2.5mm before the drop is too much?
At 20 A, about 18 m inside a 3% budget on 220 V, and about 30 m inside 5%. At 16 A it is 22 m and 38 m; at 10 A, 36 m and 61 m. The arithmetic is 6.6 V divided by (18 mV/A/m × amps), times 1,000. Ampacity is not the limit here — 2.5 mm² carries 27 A — the length is.
Voltage kam aa rahi hai — kya mota cable dalne se theek ho jaye ga?
Pehle meter par voltage naapein. Agar meter par bhi voltage kam hai to masla supply ka hai, cable ka nahin, aur mota cable us mein farq nahin dalega. Agar meter par voltage theek hai aur load par kam, to jo farq hai wohi aap ke cable ka nuqsaan hai — aur ussi ko bara conductor kam karta hai.

The cable for a long run

Two-core standard cable with the black sheath cut back to show stranded copper conductors
6MM² · 2 CORE · 450/750 V · CU CLASS 2

6mm 2 Core Standard Cable

The size most long single-phase runs land on: 7.3 mV/A/m, so 45 m at 20 A inside a 3% budget, and 46 A of capacity on method C. Class 2 stranded copper, 7/1.04, PVC insulated and sheathed to 450/750 V, drawn in Lahore.

Factory-direct price
Contact for quote
Message us for today’s rate
Send the load and the length

Cable is priced off the day's copper rate, so we quote per metre and per coil on WhatsApp. Send the size, the metres and your city: Punjab in 1–2 days, rest of Pakistan in 2–4.

Neighbouring sizes: 4mm 2 core cable price where the run is shorter, 10mm 2 core cable for a submain from the meter, and 6mm 3 core standard cable where the earth runs in the same sheath.

The size that holds the run, at the factory rate

We draw the copper in Lahore and sell it at the day's rate — no dealer margin. Send the load, the one-way run length and your city: Punjab in 1–2 days, rest of Pakistan in 2–4.

WhatsApp for advice