Add up every rated watt on the panel for the connected load, apply a diversity allowance group by group for the maximum demand, then divide by the power factor for kVA. The worked commercial unit below runs 35.7 kW connected to 26.8 kW of demand, 31.5 kVA, and 45.5 A per phase on a 400 V three-phase supply.
Nothing on a commercial panel runs flat out in the same second, so a feeder sized to the connected load buys copper that never carries current. This page stops at the amps, which is where the load calculation ends; the conductor that carries them is picked off the chart on 3-phase cable size.
Connected load is the arithmetic sum of every rated watt installed on the panel. Maximum demand is the largest load that panel will actually carry at one moment, and on any commercial installation it is the smaller of the two. The gap between them is the diversity allowance, applied group by group rather than as one blanket percentage, because shop lighting behaves nothing like a geyser. Size a commercial feeder to the maximum demand with a stated spare margin on top — sizing to an average leaves nothing for the summer peak.
The inputs come off rating plates, not off a chart. Walk the unit with the equipment list and write down what each plate says. Where a plate is missing or the equipment has not arrived, a typical figure is a placeholder to be replaced — and the one number worth chasing hardest is the air conditioning, because on a Pakistani shop or office it is usually close to half the total on its own.
One thing a maximum demand calculation is not. It is not the sanctioned load on your meter — that is the figure the utility sets when the connection is applied for, and it governs what you may draw, not what your cable must carry.
Take a real shape of building: 2,000 sq ft of retail floor on the ground with a 1,000 sq ft office above it, on a three-phase connection. Count the items, multiply by the plate rating, and total the column.
| Load group | Qty | Typical rating each | Connected |
|---|---|---|---|
| LED tube and panel lighting | 60 | 40 W | 2,400 W |
| Ceiling fans | 12 | 80 W | 960 W |
| Split AC, 1.5 ton | 6 | 1,800 W | 10,800 W |
| Split AC, 2 ton | 2 | 2,400 W | 4,800 W |
| Display chillers and refrigeration | 3 | 1,500 W | 4,500 W |
| Computers, POS terminals, printers | 12 | 300 W | 3,600 W |
| General socket outlets (allowance) | 20 | 200 W | 4,000 W |
| Electric geyser | 1 | 2,000 W | 2,000 W |
| Signage and display lighting (allowance) | — | 1,500 W | 1,500 W |
| Water pump, about 1.5 HP | 1 | 1,100 W | 1,100 W |
| Connected load | — | — | 35,660 W = 35.7 kW |
One cross-check before going further: 35,660 W spread over 3,000 sq ft is 11.9 W per sq ft. Run the same division on your own schedule. A retail-and-office figure far below that usually means a load group was missed; far above it usually means a plate rating was read as a running figure when it was a maximum.
A diversity factor is the fraction of a group's connected load that is drawing current at the same moment. Shop lighting sits at 1.0 because it is all on from opening to closing. Air conditioning sits below it because compressors cycle. A geyser and a pump sit well below, because each runs for minutes in an hour. One blanket percentage across the whole panel hides all of that, which is why the allowance is applied per group and then totalled.
| Load group | Connected | Allowance | Demand |
|---|---|---|---|
| Lighting | 2.40 kW | 1.00 | 2.40 kW |
| Ceiling fans | 0.96 kW | 1.00 | 0.96 kW |
| Air conditioning | 15.60 kW | 0.80 | 12.48 kW |
| Refrigeration | 4.50 kW | 0.80 | 3.60 kW |
| Computers and POS | 3.60 kW | 0.75 | 2.70 kW |
| General sockets | 4.00 kW | 0.40 | 1.60 kW |
| Geyser | 2.00 kW | 0.50 | 1.00 kW |
| Signage | 1.50 kW | 1.00 | 1.50 kW |
| Water pump | 1.10 kW | 0.50 | 0.55 kW |
| Maximum demand | 35.66 kW | 0.75 overall | 26.79 kW |
The overall figure falls out of the working rather than being chosen: 26.79 ÷ 35.66 = 0.75. That is the number worth writing on the drawing, because it is the one a reviewer will challenge. An allowance quoted with no schedule behind it cannot be checked by anybody, including the person who wrote it.
Cable carries current, not kilowatts, so the demand has to be converted. Three steps, all short.
Divide the demand by the power factor. 26.79 ÷ 0.85 = 31.5 kVA. That is the figure a transformer or a generator is rated in.
Amps = kVA × 1000 ÷ (√3 × 400). The denominator is 1.732 × 400 = 692.8, so 31,500 ÷ 692.8 = 45.5 A per phase.
Take 25% on top before sizing anything: 45.5 × 1.25 = 56.9 A. Design current 57 A, not 45.5 A.
Worth seeing what three phases buy. The same 26.79 kW on a 220 V single-phase supply would be 26,790 ÷ (220 × 0.85) = 143 A, which is not a shop connection — it is the reason a unit of this size is given three phases in the first place. Plant and building drawings in Pakistan often write the supply as 415 V rather than 400 V; the arithmetic here uses 400 V, which returns the higher current for the same kW and therefore the safer answer.
57 A of design current is where this calculation hands over. Take that figure, the one-way run length and the ambient the cable will sit in to the 3-phase cable size chart, which converts kW and amps into mm²; the feeder sizes we draw most often for loads of this order are listed under all standard cable sizes.
We draw the copper in Lahore and sell it at the day's rate — no dealer margin. Send the equipment list or the bill of quantities with the run length and your city: Punjab in 1–2 days, rest of Pakistan in 2–4.