Skip to content
Factory-direct from Lahore · Nationwide delivery in 2–4 days +92 319 4262451 WhatsApp

Cable size for a motor feeder — FLC, the 45°C derate, and the run

PILONE CABLES TECHNICAL TEAM

Size a motor feeder on the full-load current from the nameplate, then correct the cable's table capacity down for the ambient it actually sits in. A 20 HP motor on a 400 V three-phase supply draws roughly 28 A: that is 4 mm² against the 30°C table figure, and 6 mm² once a 45°C plant and a shared tray are allowed for.

Starting current does not move that size — it sets the starter and the protection. Length does. The same 20 HP motor 120 m from the panel needs 16 mm², two sizes above the capacity answer, because voltage drop runs out long before heat does.

Start at the nameplate, not at the chart

Every motor carries its full-load current on its plate, and that figure beats any chart because it already contains the machine's own power factor and efficiency. Read it first. Where the plate is unreadable or the motor has not arrived yet, the current can be estimated: full-load amps = HP × 746 ÷ (√3 × 400 V × power factor × efficiency). Take power factor 0.85 and efficiency 0.90 and the denominator comes to 530, so the estimate collapses to HP × 1.41. A 20 HP motor: 20 × 746 ÷ 530 = 28.2 A.

Motor feeder cable sizing in a Pakistani plant runs in three passes. The conductor must carry the motor's nameplate full-load current after the ambient and grouping correction factors have been applied to its 30°C table rating; the run must keep voltage drop inside the installation's budget, normally 3% of 400 V, which is 12 V; and the protective device must sit between the two. The starting surge is not part of the conductor sum — it is carried by the starter and the overload relay.

Plant drawings in Pakistan usually write this supply as 415 V. The arithmetic here uses 400 V, which returns the higher current for the same output and therefore the safer size; on a measured 415 V supply the real current is about 3.6% lower, since 400 ÷ 415 = 0.964.

Full-load current estimated as HP × 746 ÷ (√3 × 400 V × 0.85 × 0.90). Power factor 0.85 and efficiency 0.90 are the assumptions used for this chart, not figures read off your motor — the nameplate governs. Cable sizes are copper, PVC, three loaded conductors, current capacity per BS 7671 reference method C (clipped direct) at 30°C ambient; conductor data per IEC 60228. The last column applies a combined correction factor of 0.75, this page's worked example for a hot plant on a shared tray, not a value quoted from a standard — read your own ambient and grouping factors out of BS 7671. Verify sizing with a licensed electrician for your installation.
MotorRated outputFull-load currentSize at 30°CSize after a 0.75 correction
5 HP3.7 kW7.0 A1.5 mm²1.5 mm²
7.5 HP5.6 kW10.6 A1.5 mm²1.5 mm²
10 HP7.5 kW14.1 A1.5 mm²2.5 mm²
15 HP11.2 kW21.1 A2.5 mm²4 mm²
20 HP14.9 kW28.2 A4 mm²6 mm²
25 HP18.7 kW35.2 A6 mm²10 mm²
30 HP22.4 kW42.2 A10 mm²10 mm²
40 HP29.8 kW56.3 A10 mm²16 mm²
50 HP37.3 kW70.4 A16 mm²25 mm²
60 HP44.8 kW84.5 A25 mm²35 mm²
75 HP56.0 kW105.6 A35 mm²50 mm²
100 HP74.6 kW140.8 A50 mm²95 mm²

Two rows are worth reading twice. At 30 HP the correction changes nothing, because 10 mm² is rated 57 A and 57 × 0.75 = 42.8 A still clears the motor's 42.2 A. At 100 HP it moves the feeder two sizes, because 70 mm² comes to 184 × 0.75 = 138 A against a motor wanting 140.8 A, and three amps short is short. That is the argument for publishing the corrected column instead of a footnote.

Read the chart as a capacity answer only. On a real feeder the run usually pushes the small sizes up anyway, and on a fixed plant feeder 2.5 mm² is the sensible floor whatever the arithmetic says about a 5 HP pump.

Why 30°C is the wrong column in a Pakistani plant

Published ampacity is a laboratory number: one circuit, clipped to a wall in open air, 30°C around it. A motor feeder in a spinning shed, a compressor room or a roof-level tray in June sits nowhere near that, and it rarely sits alone. Two corrections apply, and they multiply — they do not average.

1. Ambient

The factor for the temperature the cable actually lives in, against the 30°C the table assumes. Measure the plant room in the afternoon, not the yard at night.

2. Grouping

The factor for how many other loaded circuits share the tray, ladder or conduit. Six feeders touching on one tray is a different cable from one feeder on its own.

3. Multiply, then compare

Usable current = table rating × ambient factor × grouping factor. That result, never the table figure, is what has to exceed the full-load current.

This page uses a combined 0.75 as its worked example and says so wherever it uses it. Take the real ambient and grouping factors for your temperature, your installation method and your number of grouped circuits from BS 7671. A derate is a correction applied to a stated base, so it should always be shown as base × factor = result: anyone who hands you a bare amp figure with no method and no ambient behind it has given you a number you cannot check.

Worked: a 20 HP motor, 120 m away, on a tray at 45°C

A 20 HP (14.9 kW) three-phase motor fed from the plant panel, 120 m of cable on a ladder tray beside other loaded feeders, plant ambient around 45°C. Nameplate first; failing that, the estimate is 20 × 746 ÷ 530 = 28.2 A.

Capacity pass. 4 mm² is rated 32 A for three loaded conductors at 30°C. Apply the worked 0.75 and 32 × 0.75 = 24 A, under the 28.2 A the motor draws, so it fails. 6 mm² is rated 41 A, so 41 × 0.75 = 30.8 A, which clears 28.2 A with 2.6 A to spare. On capacity alone the answer is 6 mm².

Voltage drop pass. Hold the feeder to 3% of 400 V, which is 12 V. On 6 mm² at 7.3 mV/A/m the drop is 7.3 × 28.2 × 120 ÷ 1000 = 24.7 V, twice the budget. On 10 mm² at 4.4 mV/A/m it is 4.4 × 28.2 × 120 ÷ 1000 = 14.9 V, still over. On 16 mm² at 2.8 mV/A/m it is 2.8 × 28.2 × 120 ÷ 1000 = 9.5 V, inside 12 V.

The answer is 16 mm², and it is worth noting what decided it. Heat took the cable from 4 mm² to 6 mm². Distance took it from 6 mm² to 16 mm². A feeder sized off a capacity chart alone would have gone in at 6 mm², started sluggishly, run warm at the terminals and tripped on overload in summer — with nothing visibly wrong with the cable.

One honest note on that sum. The millivolt figures used here are two-conductor values, so applying them to a balanced three-phase run overstates the drop by about 13%, since √3 ÷ 2 = 0.87. Corrected, 10 mm² still comes to 14.9 × 0.87 = 13.0 V and still misses the 12 V budget, so 16 mm² stands either way. Put your own length through the voltage drop calculator before you order.

How far each size reaches before voltage drop takes over

Capacity settles the size at the panel. Length settles it at the machine. This is the same chart read the other way round: for the corrected size in the column above, the one-way run at which the feeder spends its whole 12 V allowance.

Maximum one-way run = 12 V × 1000 ÷ (mV/A/m × full-load current), where 12 V is 3% of 400 V. Sizes are the corrected column of the chart above. Voltage drop per BS 7671, copper, PVC, two-conductor millivolt values, so a balanced three-phase run reaches roughly 15% further than shown. Some plant specifications tighten the main feeder to 2.5% — use the budget your consultant sets. Verify sizing with a licensed electrician for your installation.
MotorFull-load currentSizeVoltage dropRun at a 12 V budget
5 HP7.0 A1.5 mm²29 mV/A/m59 m
7.5 HP10.6 A1.5 mm²29 mV/A/m39 m
10 HP14.1 A2.5 mm²18 mV/A/m47 m
15 HP21.1 A4 mm²11 mV/A/m52 m
20 HP28.2 A6 mm²7.3 mV/A/m58 m
25 HP35.2 A10 mm²4.4 mV/A/m77 m
30 HP42.2 A10 mm²4.4 mV/A/m65 m
40 HP56.3 A16 mm²2.8 mV/A/m76 m
50 HP70.4 A25 mm²1.75 mV/A/m97 m
60 HP84.5 A35 mm²1.25 mV/A/m114 m
75 HP105.6 A50 mm²0.93 mV/A/m122 m
100 HP140.8 A95 mm²0.46 mV/A/m185 m

Read the 7.5 HP row against the 25 HP row. The small motor on 1.5 mm² spends its allowance at 39 m, while a motor three times its size on 10 mm² reaches 77 m. Feeder runs of 100 to 300 metres are ordinary in a large plant, and past these distances the size is chosen by the run, not by the load: go up a size and work the drop again.

Starting current: what it changes, and what it does not

A cage motor started direct-on-line pulls a heavy surge for a few seconds — as a rule of thumb six to eight times full-load current, though the figure to trust is the motor's own data or the starter's setting. For the 20 HP motor above that is roughly 28.2 × 6 = 169 A up to 28.2 × 8 = 226 A, against a cable chosen for 28.2 A.

That does not mean the cable is undersized. The surge lasts seconds, conductor heating is a matter of minutes, and the copper rides it. What the surge decides is everything around the cable: the protective device has to be motor-rated so it does not trip on inrush, the overload relay is set to the running current rather than the surge, and a star-delta starter, a soft starter or a drive cuts the peak where the supply is weak.

The one place the surge does reach the cable is voltage drop at the instant of starting. A feeder already at the edge of its 12 V budget when running sags much harder on inrush, and the symptom is a motor that hums, struggles and trips instead of spinning up. That is a run-length problem wearing a motor's clothes, and a size up is the fix. A drive-fed motor is a separate specification again: the drive maker states the cable type and a maximum length, and that instruction outranks any chart.

Sizing a plant submain rather than one motor

A submain feeding a shed of machines is not the sum of every nameplate. Total the full-load currents, apply a diversity allowance because the whole plant never runs flat out in the same second, and size against the diversified figure — then check the run, which on a factory submain is usually the constraint that decides the answer. The load total itself is a separate calculation, worked through on commercial load calculation, and the kW-to-mm² chart for a whole three-phase load sits on 3-phase cable size.

Current capacity depends on how and where the cable is installed. Every figure on this page is a 30°C, method C, clipped-direct base rating corrected by a stated example factor of 0.75 — substitute the ambient and grouping factors BS 7671 gives for your own plant. A wrong motor feeder fails harder than a wrong house circuit: have a licensed electrician confirm the load, the derating and the protection before the cable is cut, or start with the cable size calculator.

The cable for a motor feeder

Three-phase feeders run as four-core where the earth travels with the phases, or three-core with a separate earth conductor. These are the sizes the chart lands on most often; the worked 20 HP example at 120 m ends on 16mm 4 core cable.

Where the earth runs separately, the three-core versions are 10mm 3 core cable, 16mm 3 core cable and 25mm 3 core cable. For the longest plant distribution runs, where cost per metre matters more than cross-section, compare aluminium cable. Send the sizes and the metres, and we will confirm what we can supply and today's rate.

Frequently asked

What cable size for a 20 HP motor?
About 28 A at 400 V three-phase, so 4 mm² against the 30°C table figure and 6 mm² once a 45°C plant and a shared tray are corrected for. Length then decides: past roughly 58 m the 12 V budget runs out and the size goes up, and at 120 m the answer is 16 mm². Read the nameplate before any of this.
Does motor starting current change the cable size?
No. A direct-on-line start pulls six to eight times full-load current as a rule of thumb, but only for seconds, and the copper rides it. The surge sets the starter, the overload relay and the protective device instead. It reaches the cable only through voltage drop at the instant of starting, which is a run-length problem, not a capacity one.
The chart says 30 degrees. Do I have to derate for a 45 degree plant?
Yes, and for grouping as well. Published capacity assumes one circuit clipped in open air at 30°C. Usable current = table rating × ambient factor × grouping factor, and the corrected number is what must exceed the motor's full-load current. This page shows a combined 0.75 as an example; take your own factors from BS 7671 for your ambient and your tray.
Motor ki cable ka size kaise nikalte hain?
Pehle motor ki plate par likha full-load current dekhein. Phir table ki rating ko garmi aur grouping ke factor se kam karein, kyunke 30°C wali figure Pakistani plant ke liye nahi banai gayi. Aakhir mein run length check karein: 400 V par 3% ka matlab 12 volt hai. 20 HP ki motor takreeban 28 A kheenchti hai.
How much voltage drop is allowed on a long factory feeder?
Take 3% of the supply as the working budget, so 12 V on a 400 V system. Some plant specifications tighten a main feeder to 2.5%, which is 10 V, and the figure your consultant sets is the one that counts. The sum is mV/A/m × amps × one-way metres ÷ 1000, and past about 100 m it is this, not heat, that picks the size.
What size is a factory submain cable?
It is not the sum of every nameplate on the panel. Total the full-load currents, apply a diversity allowance because the plant never runs flat out at once, then size against that figure and check the run. On a long factory submain the run usually decides it. The load total itself is worked through on the commercial load calculation guide.
Copper or aluminium for a factory submain?
Copper for machine feeds and for anything landing on small equipment terminals. Aluminium earns its place on the longest plant distribution runs, where the cost per metre matters more than the extra cross-section it needs to carry the same current. It is a size-for-size comparison rather than a like-for-like swap, and the capacity by size is on the aluminium cable page.

Send the motor schedule, get it priced line by line

We draw the copper in Lahore and sell it at the day's rate — no dealer margin. Send the motor list with HP, run lengths and routing, or a bill of quantities, and it comes back priced: Punjab in 1–2 days, rest of Pakistan in 2–4.

WhatsApp the schedule