Plan the cable quantities for a 5-marla house

PILONE CABLES TECHNICAL TEAM · UPDATED 2 OCTOBER 2026

A 5-marla plot does not determine a fixed number of cable coils.

Prepare a circuit schedule using floors, covered area, appliances and measured routes. This page explains how to turn that schedule into cable metres and a quotation request; it is not a final bill of materials.

Start with the house plan, then calculate metres

Record the local plot dimensions and covered floor area from the drawing. Marla area conventions can vary, and plot area is not the same as the area being wired.

The distribution-board locations, floor count, circuit layout and high-load appliances determine the routes. Two houses on the same plot size can require different quantities.

Prepare the electrical design with an electrician before ordering. Confirm the cable sizes and conductor arrangements circuit by circuit, then measure lengths.

How to build a measured cable schedule

Use the approved point and circuit layout as the starting point. The three steps below produce a schedule that can be checked and revised.

Count circuits and points

List lights, fans, sockets and appliances by room and floor. Identify dedicated circuits from the electrical design.

Measure each route

Measure along the intended conduit, including vertical runs, switch drops and distribution-board connections.

Count actual conductors

Record line, neutral, protective and control conductors for each segment. Avoid a fractional average or counting a shared segment twice.

For a single-core route, add the length of each conductor actually required. Illustrative arithmetic only: three separately installed conductors on the same 12 m route total 36 conductor-metres before termination allowances. A 12 m run of three-core cable is 12 cable-metres, not 36.

Total each size and construction separately, including agreed allowances once. See house cable quantity planning and confirm all assumptions against your own layout.

5-marla house wiring cable schedule

A planning checklist, not prescribed cable sizes or quantities. Linked sizes are catalogue examples to compare only after the design is confirmed.
Circuit / routeCatalogue examplesQuantity methodSelection checks
Lights and fans1.5 mm² cableMeasure each required conductor and switch dropLoad, protection, installation and voltage drop
Sockets and kitchen2.5 mm² cableTotal the designed circuit routesCircuit arrangement and appliance loads
AC, geyser and pump4 mm² cableMeasure each dedicated routeNameplate data and manufacturer requirements
EarthingEarth cable rangeMeasure designed protective/bonding routesProtective conductor sizing and fault conditions
Meter and board feedersStandard cable rangeMeasure feeder and riser routesDemand, phase arrangement, protection and utility requirements
Send your floor plan or room count for a cable quote.

Record points room by room

Use the actual room layout. A standard room count, point density or fixed covered area is not assumed for every 5-marla house.

Fill these categories from the approved layout; no point totals are assumed.
AreaLighting / fansSocketsAppliances
BedroomsCount on drawingCount on drawingList each AC or other load
Lounge / drawing roomCount on drawingCount on drawingList dedicated loads
KitchenCount on drawingIdentify intended loadsRecord nameplates where relevant
BathroomsCount on drawingCheck applicable location rulesGeyser / exhaust requirements
Porch, stairs and outsideCount by floor and routeConfirm weather exposurePump and outdoor loads

Have the point schedule checked before finishes conceal the routes. This reduces missing circuits and duplicated allowances.

Single-storey and double-storey quantities

Calculate each floor and shared feeder separately. Adding a floor does not justify a fixed multiplier: board positions, appliance loads and riser lengths can change the design.

How the schedule changes when another floor is added.
ItemSingle storeyAdditional floor
Final circuitsUse ground-floor planUse upper-floor plan
Distribution boardsRecord designed locationsConfirm whether another board is required
Risers / feedersMeasure actual incoming routeMeasure vertical and horizontal segments
Main demandAssess the planned loadsReassess demand and protection
Cable totalSum by size and constructionCombine schedules without double-counting shared routes

Meter-to-board and distribution-board feeders

Include the incoming feeder, any board-to-board risers and the earthing arrangement in the schedule. Their sizes depend on assessed demand, supply arrangement and protection, not plot area alone.

Confirm the route, utility requirements and selected construction with the electrician. Browse standard cable for quotation options and Lahore cable buying information for the local enquiry path.

Strand codes and nominal cable sizes

Write the nominal size and construction on the order. A trade code can help identify an enquiry, but it does not replace a declared specification. The strand-code guide explains the distinction.

Calculated geometry for the stated inch-based notation, rounded only at the end. Diameter is per strand; area is the sum of strand areas, not overall cable diameter, nominal compliance or an amp rating. Product links identify catalogue entries, not certified metric equivalents.
Code / productStated buildStrand diameterCalculated areaNominal sizeBefore ordering
3/293 × 0.029 in0.7366 mm1.28 mm²Confirm the marked nominal mm²Confirm material and construction
7/297 × 0.029 in0.7366 mm2.98 mm²Confirm the marked nominal mm²Confirm material and construction
7/367 × 0.036 in0.9144 mm4.60 mm²Confirm the marked nominal mm²Confirm material and construction
7/447 × 0.044 in1.1176 mm6.87 mm²Confirm the marked nominal mm²Confirm material and construction
7/527 × 0.052 in1.3208 mm9.59 mm²Confirm the marked nominal mm²Confirm material and construction
7/647 × 0.064 in1.6256 mm14.53 mm²Confirm the marked nominal mm²Confirm material and construction

The inch-based formula calculates metal geometry only. A supplier’s nominal mm² declaration and the relevant compliance tests are separate.

Check the delivered cable and length

Compare the label and quotation: cable family, material, nominal size, conductor class, core count and insulation specification.

Check the delivered length against the stated metres. Coil or drum is a packaging description, not a guaranteed length.

Counting strands and measuring their diameter can check stated geometry, but it does not establish resistance compliance or the cable’s permissible current.

If test evidence is needed, request the relevant datasheet or report and have it assessed by a qualified person. A casual resistance reading is not a reliable substitute for measuring delivered length.

Record any cutting or termination allowance separately and agree how lengths will be supplied before purchase.

Cable sizing and protection checks

Selection checks for the circuit schedule. This is not a table of universal cable or breaker ratings.
CircuitLoad informationInstallation informationProtection
Lighting / fansDesigned lighting loadRouting and groupingCoordinate with selected cable
Sockets / kitchenExpected demand and appliancesCircuit arrangement and installationCheck required protective measures
AC / geyser / pumpModel-specific electrical dataDedicated routes and starting conditionsManufacturer and installation requirements
FeedersAssessed demand by floorLength, grouping and supply arrangementOverload and fault checks
Protective conductorsEarthing and bonding designActual conductor routesFault/disconnection verification

Cable size and quantity are separate decisions. Use the cable-size calculator for planning; have a licensed electrician verify the design. References: Schneider Electric: cable sizing and installation conditions; Schneider Electric: protective-device selection.

What a house-wiring quotation includes

Compare quotations with the same scope. A cable-only quotation cannot be compared directly with a total that includes conduit, accessories and labour.

Ask each supplier or installer to identify which scope is priced.
ScopeIncludesConfirm separately
Cable onlySpecified cable and supplied metresUnit rate, taxes, delivery and length
Cable and materialsCable plus agreed accessoriesConduit, boards, devices and fittings
Installed workAgreed materials and labourTesting, scope exclusions and completion terms

For coil ordering, divide the required metres for each size and construction by the supplier-confirmed coil length, rounding up only when whole coils are required. Ask whether cut lengths are offered; do not assume a universal coil length.

These are planning quantities worked from a stated point count, run length and conductor count — not a certified load calculation. Current capacities assume method C at 30°C; derate for conduit, bunching and summer ambient. Confirm the point schedule, circuit count and every cable size with a licensed electrician against your approved layout, or start with the cable size calculator.

Frequently asked

How many coils does a 5-marla house need?
There is no fixed count. Calculate the circuits and measured conductor routes for the actual floors, covered area and appliances, then convert to the supplier-confirmed coil lengths.
Is a 5-marla wiring list a final bill of materials?
No. A quotation schedule needs the approved electrical layout, selected specifications and measured quantities. Plot size alone is insufficient.
Does double storey mean twice the cable?
Not necessarily. Measure the upper-floor circuits and shared risers separately, then reassess the incoming supply and demand.
How many points should I assume?
Count them from the room and electrical layouts. Include appliances and external areas without imposing a standard point count.
What distribution-board size is required?
The circuit schedule, protective devices, supply arrangement and planned spare capacity determine the board. Ask the electrician to specify it.
Is every coil 90 metres?
No. Confirm the supplied length on the quotation and label. Divide metres by that length only when ordering whole coils.
Which cable should be used for a 1.5-ton AC?
Use the model’s electrical requirements and installation details. See the 1.5-ton AC guide for the information needed.

Compare the cable listed in your schedule

Coil of 7/.029 single-core PVC-insulated copper house wiring cable
7/.029 · SINGLE CORE · CONFIRM NOMINAL SPECIFICATION

7/.029 Single Core Copper Cable

This catalogue entry can help identify a strand-code enquiry. Confirm its nominal specification and the required metres against the approved circuit schedule.

Factory-direct price
Contact for quote
Message us for today’s rate
Send your floor plan or room count for a cable quote.

Send the planned quantities by size and construction, together with the delivery city.

Compare 1.5 mm², 2.5 mm² and 4 mm² catalogue options after selection, plus earth cable and feeders. These links are not a prescribed house cable list.