Single storey, 90 m coils: 3 marla takes about 11 coils, 5 marla 21, 7 marla 29, 10 marla 43, 1 kanal 71 and 2 kanal 125.
Every one of those figures is the point count of that plot size multiplied by an average run and a conductor count, with 15% cut in for wastage, then divided by 90. The split across sizes and the arithmetic behind each row are in the master table below. Nothing here is a price, and nothing here is a substitute for counting the points on your own approved layout.
One table, six plot sizes, five conductor sizes. The three coil columns are what you order by the coil; the 6 mm² and 10 mm² columns are cut lengths, because the earth conductor and the meter run are measured, not coiled. Every row is reproduced from that plot size's own guide, linked in the first column.
| Plot size | Points | 1.5 mm² | 2.5 mm² | 4 mm² | 6 mm² earth | 10 mm² service | Total coils | Conductor metres |
|---|---|---|---|---|---|---|---|---|
| 3 marla | 28 | 6 coils | 4 coils | 1 coil | 17 m cut | 18 m cut | 11 | 905 m |
| 5 marla | 46 | 10 coils | 9 coils | 2 coils | 23 m cut | 22 m cut | 21 | 1,793 m |
| 7 marla | 60 | 14 coils | 12 coils | 3 coils | 25 m cut | steps to 16 mm² | 29 | 2,522 m |
| 10 marla | 78 | 20 coils | 18 coils | 5 coils | 29 m cut | steps to 16 mm² | 43 | 3,779 m |
| 1 kanal | 110 | 34 coils | 30 coils | 7 coils | 35 m cut | steps to 25 mm² | 71 | 6,324 m |
| 2 kanal | 160 | 60 coils | 53 coils | 12 coils | 46 m cut | steps to 16 mm² 4 core | 125 | 11,232 m |
Single-storey house wiring quantities by plot size. Coils at 90 m, rounded up per size; 15% wastage included; conduit wiring; a centrally placed distribution board. Point counts are typical schedules for each plot size, not your layout. Sizes are named in mm². These are planning bands, not a bill of quantities — verify the schedule and every cable size with a licensed electrician against your approved plan. Strand codes: 1.5 mm² = 3/.029, 2.5 mm² = 7/.029, 4 mm² = 7/.036, 6 mm² = 7/.044, 10 mm² = 7/.052.
Read the 10 mm² column carefully, because it is the one that trips people up. 10 mm² is not a house circuit on this table — it is the service run from the meter to the distribution board, and it is sized against the sanctioned load, not the plot. It holds at 3 and 5 marla, then steps up. The full service ladder is two tables down.
This page adds no new arithmetic. Each row is lifted unchanged from the guide that works it out, so a figure you quote from here can be traced to the point schedule that produced it.
A house wiring quantity is not read off the plot size. It is three numbers multiplied, and the plot size only sets their typical values. Change any one and the table moves, which is exactly why the inputs are printed rather than hidden.
Light and fan points, socket points, appliance points. This is the input with the most leverage, and the only one you can read off your own approved layout today.
The conduit length attributable to one point: its share of the circuit run back to the board, plus the ceiling rise and the switch drop. 10 m on 3 marla, 12 m on 5 marla, rising with the floor plate.
2.5 on lighting and fan circuits, where switch legs share neutrals. 3 on socket and appliance circuits, which each carry live, neutral and earth.
Worked on the 5 marla row: lighting and fans 24 × 12 × 2.5 = 720 m; sockets and kitchen 18 × 12 × 3 = 648 m; pump on a 15 m run 1 × 15 × 3 = 45 m; two ACs and a geyser on 14 m runs 3 × 14 × 3 = 126 m of 4 mm²; main earth 20 m. Raw total 1,559 m. Add 15% for cutting waste and failed pulls: 1,559 × 1.15 = 1,793 m. Divide by 90 and round up per size and you have 10 + 9 + 2 = 21 coils.
Cross-check any row against the trade rule of 1.5–2 ft of conduit run per sq ft of plot, at 2–3 conductors per run. On a 1,125 sq ft 5 marla plot that band is roughly 1,000–2,000 m of conductor, and 1,793 m sits inside it. If a published quantity for your plot size sits far outside this table, ask what point count and run length it assumed. If it states neither, it cannot be compared with this one. Adjust the whole thing to your own house on how much cable a house needs.
Most plots in Pakistan are built upward. The upper floor carries about 85% of the ground floor's points — no porch, no main entrance, no pump — and adds a riser from the ground board to a second board upstairs. That riser is a separate cut length, not a coil.
| Plot size | Points | 1.5 mm² | 2.5 mm² | 4 mm² | Total coils | Conductor metres | Riser or sub-mains |
|---|---|---|---|---|---|---|---|
| 3 marla | 52 | 10 | 8 | 2 | 20 | 1,675 m | 10 mm², about 10 m |
| 5 marla | 85 | 18 | 17 | 3 | 38 | 3,317 m | 10 mm², about 12 m |
| 7 marla | 111 | 25 | 22 | 6 | 53 | 4,666 m | 16 mm², about 14 m |
| 10 marla | 144 | 36 | 34 | 9 | 79 | 6,991 m | 16 mm², about 16 m |
| 1 kanal | 204 | 63 | 56 | 12 | 131 | 11,699 m | 16 mm², about 85 m |
| 2 kanal | 296 | 111 | 98 | 23 | 232 | 20,779 m | 16 mm², about 190 m |
Lay the riser conduit before the plaster goes on, even if the upper floor is years away. An empty 25 mm pipe from the ground board to the roof slab costs almost nothing during construction and a wall afterwards. The build sequence is on wiring for a new house, and a floor that will be rented is a different circuit design again — see the apartment and portion wiring guide.
The coil list wires the house. It does not feed it. The run from the WAPDA or K-Electric meter to your distribution board is a separate, heavier cable, and it is the line missing from almost every published wiring quantity. It is sized against the sanctioned load on your meter card, which is why it does not track the plot size neatly.
| Plot size | Load assumed | Current | Service cable | Run |
|---|---|---|---|---|
| 3 marla | 5 kW | 22.7 A | 10 mm² 2 core | 18 m / 60 ft |
| 5 marla | 7.5 kW | 34.1 A | 10 mm² 2 core | 22 m / 72 ft |
| 7 marla | 10 kW | 45.5 A | 16 mm² 2 core | 25 m / 82 ft |
| 10 marla | 12 kW | 54.5 A | 16 mm² 2 core | 28 m / 92 ft |
| 1 kanal | 15 kW | 68.2 A | 25 mm² 2 core, or 10 mm² 4 core on three phase | 32 m / 105 ft |
| 2 kanal | 25 kW | 36.1 A per phase | 16 mm² 4 core, three phase | 40 m / 131 ft |
The 1 kanal row shows why the phase decision comes before the cable decision. At a 15 kW sanctioned load, single phase draws 68.2 A and needs 25 mm²; split across three phases at 400 V the same load is 15,000 ÷ (400 × 1.732) = 21.6 A per phase, a third of that current per conductor, and 10 mm² four-core carries it. The 2 kanal row is the same effect at 25 kW: 113.6 A on one phase against 36.1 A on three. The sizing rationale in full is on WAPDA meter cable size and main meter cable; the K-Electric case is on K-Electric meter cable.
Quantities are only half the list. The other half is whether the size against each circuit is the right one, and that is a current capacity question, not a metres question.
| Size | Strand code | 2 loaded cores | 3 loaded cores | Voltage drop | Class 2 strands | Resistance | Copper per 90 m coil | Usual job |
|---|---|---|---|---|---|---|---|---|
| 1.5 mm² | 3/.029 | 19.5 A | 17.5 A | 29 mV/A/m | 7/0.53 | 12.1 Ω/km | 1.20 kg | Lights, fans |
| 2.5 mm² | 7/.029 | 27 A | 24 A | 18 mV/A/m | 7/0.67 | 7.41 Ω/km | 2.00 kg | Sockets, kitchen, pump |
| 4 mm² | 7/.036 | 36 A | 32 A | 11 mV/A/m | 7/0.85 | 4.61 Ω/km | 3.20 kg | AC points, geyser |
| 6 mm² | 7/.044 | 46 A | 41 A | 7.3 mV/A/m | 7/1.04 | 3.08 Ω/km | 4.80 kg | Main earth, sub-mains |
| 10 mm² | 7/.052 | 63 A | 57 A | 4.4 mV/A/m | 7/1.35 | 1.83 Ω/km | 8.00 kg | Meter to DB, risers |
| 16 mm² | 7/.064 | 85 A | 76 A | 2.8 mV/A/m | 7/1.70 | 1.15 Ω/km | 12.80 kg | Heavier service, sub-mains |
| 25 mm² | 19/.052 | 112 A | 96 A | 1.75 mV/A/m | 7/2.14 | 0.727 Ω/km | 20.00 kg | 1 kanal single-phase service |
The strand codes are imperial and do not land exactly on the metric areas they are sold as: 3/.029 computes to 1.28 mm² against a nominal 1.5, 7/.029 to 2.98 mm² against a nominal 2.5, 7/.036 to 4.60 mm² against a nominal 4, 7/.044 to 6.87 mm², 7/.052 to 9.59 mm² and 7/.064 to 14.53 mm². We label to the same market convention everyone else does, and we publish both numbers so you can see which one you are buying. 25 mm² is sold under the code 19/.052 — nineteen strands of 0.052 inch, 26.03 mm² — and its IEC 60228 class 2 stranding is 7/2.14, in millimetres. Read the first two rows before you order: 3/.029 sits under a true 1.5 mm², so keep it behind 6 A lighting breakers and off sockets.
A 1 kanal list is 71 coils of copper taken on trust. It does not have to be. Conductor mass is arithmetic, not opinion: area in mm² × 8.89 kg/km per mm² × 0.090 km per coil. A 90 m coil of 2.5 mm² holds 2.00 kg of copper before any insulation. Weigh the coil, subtract a reasonable allowance for the PVC, and you have a check anyone can run with a bathroom scale.
| Plot size | Coil list (1.5 + 2.5 + 4) | Copper in the list |
|---|---|---|
| 3 marla | 6 + 4 + 1 | 18.40 kg |
| 5 marla | 10 + 9 + 2 | 36.40 kg |
| 7 marla | 14 + 12 + 3 | 50.40 kg |
| 10 marla | 20 + 18 + 5 | 76.00 kg |
| 1 kanal | 34 + 30 + 7 | 123.20 kg |
| 2 kanal | 60 + 53 + 12 | 216.40 kg |
Two more checks cost nothing. Count the strands: strip 30 mm and count — 3/.029 has three, 7/.029 has seven, and a conductor sold as seven-strand with six strands is not that conductor whatever the label says. Measure one strand: a caliper should read about 0.74 mm on a .029 code, 0.91 mm on .036 and 1.32 mm on .052, and area = strands × π/4 × diameter². Seven strands at 0.9144 mm give 4.60 mm², which is what 7/.036 should be. Why the weight and the strand count matter more than the sticker is set out on how cable is priced in Pakistan.
Every technical source quotes house wiring in metres. Every shop in Pakistan sells it in coils. The conversion is metres ÷ 90, rounded up per size, because nobody cuts you a 1,793 m length — you buy 10 coils of 1.5 mm² and hold the offcut. That rounding is why the coil columns and the metre column do not reconcile exactly, and it is deliberate.
Confirm the coil length in writing before you order, from us or anyone else. A coil is conventionally 90 m and near enough 100 yards, but 45 m and 30 m coils exist, and a coil quoted in feet needs converting — 301 ft is 91.7 m, 1 m is 3.281 ft. The word "coil" is not a fixed quantity, and it is the number that quietly varies between suppliers.
Do not shave the list. The gap between 21 coils and 18 is three coils of copper and a circuit you cannot add later without opening plaster. On any plot size, the wire is the cheapest part of the wall it sits in.
This table is a starting band. Three tools take it to your house.
The same three inputs, circuit by circuit, with your own point count instead of a typical one.
Load in watts or amps, run length and installation method to a conductor size, with the derating applied.
The check that decides long runs, in mV/A/m against your actual metres and your supply voltage.
Sizing one circuit rather than a whole house? The selection chart is on single-phase cable size, three-phase distribution is on 3 phase cable size, and the AC circuit is worked through end to end on cable for a 1.5 ton AC. What the labour and fittings add on top of the coil list is on cable installation cost.
We draw the copper in Lahore and sell it at the day's rate — no dealer margin, and the line that made the coil answers the message. Send your plot size or your own coil list with your city: Punjab in 1–2 days, rest of Pakistan in 2–4.