Skip to content
Factory-direct from Lahore · Nationwide delivery in 2–4 days +92 319 4262451 WhatsApp

House wiring cable quantities in Pakistan, 3 marla to 2 kanal

BY PILONE CABLES TECHNICAL TEAM

Single storey, 90 m coils: 3 marla takes about 11 coils, 5 marla 21, 7 marla 29, 10 marla 43, 1 kanal 71 and 2 kanal 125.

Every one of those figures is the point count of that plot size multiplied by an average run and a conductor count, with 15% cut in for wastage, then divided by 90. The split across sizes and the arithmetic behind each row are in the master table below. Nothing here is a price, and nothing here is a substitute for counting the points on your own approved layout.

The quantity master table

One table, six plot sizes, five conductor sizes. The three coil columns are what you order by the coil; the 6 mm² and 10 mm² columns are cut lengths, because the earth conductor and the meter run are measured, not coiled. Every row is reproduced from that plot size's own guide, linked in the first column.

Plot sizePoints1.5 mm²2.5 mm²4 mm²6 mm² earth10 mm² serviceTotal coilsConductor metres
3 marla286 coils4 coils1 coil17 m cut18 m cut11905 m
5 marla4610 coils9 coils2 coils23 m cut22 m cut211,793 m
7 marla6014 coils12 coils3 coils25 m cutsteps to 16 mm²292,522 m
10 marla7820 coils18 coils5 coils29 m cutsteps to 16 mm²433,779 m
1 kanal11034 coils30 coils7 coils35 m cutsteps to 25 mm²716,324 m
2 kanal16060 coils53 coils12 coils46 m cutsteps to 16 mm² 4 core12511,232 m

Single-storey house wiring quantities by plot size. Coils at 90 m, rounded up per size; 15% wastage included; conduit wiring; a centrally placed distribution board. Point counts are typical schedules for each plot size, not your layout. Sizes are named in mm². These are planning bands, not a bill of quantities — verify the schedule and every cable size with a licensed electrician against your approved plan. Strand codes: 1.5 mm² = 3/.029, 2.5 mm² = 7/.029, 4 mm² = 7/.036, 6 mm² = 7/.044, 10 mm² = 7/.052.

Read the 10 mm² column carefully, because it is the one that trips people up. 10 mm² is not a house circuit on this table — it is the service run from the meter to the distribution board, and it is sized against the sanctioned load, not the plot. It holds at 3 and 5 marla, then steps up. The full service ladder is two tables down.

Where each row comes from

This page adds no new arithmetic. Each row is lifted unchanged from the guide that works it out, so a figure you quote from here can be traced to the point schedule that produced it.

The three inputs that move every figure

A house wiring quantity is not read off the plot size. It is three numbers multiplied, and the plot size only sets their typical values. Change any one and the table moves, which is exactly why the inputs are printed rather than hidden.

1. Points

Light and fan points, socket points, appliance points. This is the input with the most leverage, and the only one you can read off your own approved layout today.

2. Average run per point

The conduit length attributable to one point: its share of the circuit run back to the board, plus the ceiling rise and the switch drop. 10 m on 3 marla, 12 m on 5 marla, rising with the floor plate.

3. Conductors per run

2.5 on lighting and fan circuits, where switch legs share neutrals. 3 on socket and appliance circuits, which each carry live, neutral and earth.

Worked on the 5 marla row: lighting and fans 24 × 12 × 2.5 = 720 m; sockets and kitchen 18 × 12 × 3 = 648 m; pump on a 15 m run 1 × 15 × 3 = 45 m; two ACs and a geyser on 14 m runs 3 × 14 × 3 = 126 m of 4 mm²; main earth 20 m. Raw total 1,559 m. Add 15% for cutting waste and failed pulls: 1,559 × 1.15 = 1,793 m. Divide by 90 and round up per size and you have 10 + 9 + 2 = 21 coils.

Cross-check any row against the trade rule of 1.5–2 ft of conduit run per sq ft of plot, at 2–3 conductors per run. On a 1,125 sq ft 5 marla plot that band is roughly 1,000–2,000 m of conductor, and 1,793 m sits inside it. If a published quantity for your plot size sits far outside this table, ask what point count and run length it assumed. If it states neither, it cannot be compared with this one. Adjust the whole thing to your own house on how much cable a house needs.

The same table for a double storey

Most plots in Pakistan are built upward. The upper floor carries about 85% of the ground floor's points — no porch, no main entrance, no pump — and adds a riser from the ground board to a second board upstairs. That riser is a separate cut length, not a coil.

Double-storey quantities by plot size. Second-floor figures derived as 0.85 of the ground floor plus the riser; coils at 90 m, rounded up per size; 15% wastage included. The 1 kanal and 2 kanal rows carry sub-mains to sub-boards rather than a single riser. Planning bands, not a bill — confirm against your approved layout with a licensed electrician.
Plot sizePoints1.5 mm²2.5 mm²4 mm²Total coilsConductor metresRiser or sub-mains
3 marla521082201,675 m10 mm², about 10 m
5 marla8518173383,317 m10 mm², about 12 m
7 marla11125226534,666 m16 mm², about 14 m
10 marla14436349796,991 m16 mm², about 16 m
1 kanal20463561213111,699 m16 mm², about 85 m
2 kanal296111982323220,779 m16 mm², about 190 m

Lay the riser conduit before the plaster goes on, even if the upper floor is years away. An empty 25 mm pipe from the ground board to the roof slab costs almost nothing during construction and a wall afterwards. The build sequence is on wiring for a new house, and a floor that will be rented is a different circuit design again — see the apartment and portion wiring guide.

The service cable, meter to distribution board

The coil list wires the house. It does not feed it. The run from the WAPDA or K-Electric meter to your distribution board is a separate, heavier cable, and it is the line missing from almost every published wiring quantity. It is sized against the sanctioned load on your meter card, which is why it does not track the plot size neatly.

Service run by plot size. Sanctioned loads are the typical figures assumed on each plot-size guide — take the real one off your meter card. Single-phase current = W ÷ 220 V; three-phase current = W ÷ (400 × 1.732). Current capacity per BS 7671 (IEC 60364-5-52), reference method C (clipped direct), 30°C ambient, PVC, copper; conductor data per IEC 60228. Derate for conduit, bunching and summer ambient. Verify with a licensed electrician for your installation.
Plot sizeLoad assumedCurrentService cableRun
3 marla5 kW22.7 A10 mm² 2 core18 m / 60 ft
5 marla7.5 kW34.1 A10 mm² 2 core22 m / 72 ft
7 marla10 kW45.5 A16 mm² 2 core25 m / 82 ft
10 marla12 kW54.5 A16 mm² 2 core28 m / 92 ft
1 kanal15 kW68.2 A25 mm² 2 core, or 10 mm² 4 core on three phase32 m / 105 ft
2 kanal25 kW36.1 A per phase16 mm² 4 core, three phase40 m / 131 ft

The 1 kanal row shows why the phase decision comes before the cable decision. At a 15 kW sanctioned load, single phase draws 68.2 A and needs 25 mm²; split across three phases at 400 V the same load is 15,000 ÷ (400 × 1.732) = 21.6 A per phase, a third of that current per conductor, and 10 mm² four-core carries it. The 2 kanal row is the same effect at 25 kW: 113.6 A on one phase against 36.1 A on three. The sizing rationale in full is on WAPDA meter cable size and main meter cable; the K-Electric case is on K-Electric meter cable.

What each size on the table carries

Quantities are only half the list. The other half is whether the size against each circuit is the right one, and that is a current capacity question, not a metres question.

Copper conductors, PVC insulated, 450/750 V. Current capacity and voltage drop per BS 7671 (IEC 60364-5-52), installation reference method C (clipped direct), 30°C ambient, PVC 70°C conductor; DC resistance at 20°C and class 2 stranding per IEC 60228. Wire pulled through conduit and bunched in a Lahore summer carries less than this — derate it. Copper mass is the conductor only, before insulation: nominal area × 8.89 kg/km per mm² × 0.090 km. Verify sizing with a licensed electrician for your installation.
SizeStrand code2 loaded cores3 loaded coresVoltage dropClass 2 strandsResistanceCopper per 90 m coilUsual job
1.5 mm²3/.02919.5 A17.5 A29 mV/A/m7/0.5312.1 Ω/km1.20 kgLights, fans
2.5 mm²7/.02927 A24 A18 mV/A/m7/0.677.41 Ω/km2.00 kgSockets, kitchen, pump
4 mm²7/.03636 A32 A11 mV/A/m7/0.854.61 Ω/km3.20 kgAC points, geyser
6 mm²7/.04446 A41 A7.3 mV/A/m7/1.043.08 Ω/km4.80 kgMain earth, sub-mains
10 mm²7/.05263 A57 A4.4 mV/A/m7/1.351.83 Ω/km8.00 kgMeter to DB, risers
16 mm²7/.06485 A76 A2.8 mV/A/m7/1.701.15 Ω/km12.80 kgHeavier service, sub-mains
25 mm²19/.052112 A96 A1.75 mV/A/m7/2.140.727 Ω/km20.00 kg1 kanal single-phase service

The strand codes are imperial and do not land exactly on the metric areas they are sold as: 3/.029 computes to 1.28 mm² against a nominal 1.5, 7/.029 to 2.98 mm² against a nominal 2.5, 7/.036 to 4.60 mm² against a nominal 4, 7/.044 to 6.87 mm², 7/.052 to 9.59 mm² and 7/.064 to 14.53 mm². We label to the same market convention everyone else does, and we publish both numbers so you can see which one you are buying. 25 mm² is sold under the code 19/.052 — nineteen strands of 0.052 inch, 26.03 mm² — and its IEC 60228 class 2 stranding is 7/2.14, in millimetres. Read the first two rows before you order: 3/.029 sits under a true 1.5 mm², so keep it behind 6 A lighting breakers and off sockets.

Checking the copper that arrives

A 1 kanal list is 71 coils of copper taken on trust. It does not have to be. Conductor mass is arithmetic, not opinion: area in mm² × 8.89 kg/km per mm² × 0.090 km per coil. A 90 m coil of 2.5 mm² holds 2.00 kg of copper before any insulation. Weigh the coil, subtract a reasonable allowance for the PVC, and you have a check anyone can run with a bathroom scale.

Conductor copper in each plot size's single-storey coil list. Per-coil mass = IEC 60228 nominal area × 8.89 kg/km per mm² × 0.090 km, giving 1.20 kg on 1.5 mm², 2.00 kg on 2.5 mm² and 3.20 kg on 4 mm². Totals are those three figures times the coil counts, so you can reproduce every row by hand. Conductor only: PVC insulation, the earth conductor and the service cable are on top of this.
Plot sizeCoil list (1.5 + 2.5 + 4)Copper in the list
3 marla6 + 4 + 118.40 kg
5 marla10 + 9 + 236.40 kg
7 marla14 + 12 + 350.40 kg
10 marla20 + 18 + 576.00 kg
1 kanal34 + 30 + 7123.20 kg
2 kanal60 + 53 + 12216.40 kg

Two more checks cost nothing. Count the strands: strip 30 mm and count — 3/.029 has three, 7/.029 has seven, and a conductor sold as seven-strand with six strands is not that conductor whatever the label says. Measure one strand: a caliper should read about 0.74 mm on a .029 code, 0.91 mm on .036 and 1.32 mm on .052, and area = strands × π/4 × diameter². Seven strands at 0.9144 mm give 4.60 mm², which is what 7/.036 should be. Why the weight and the strand count matter more than the sticker is set out on how cable is priced in Pakistan.

Turning the table into an order

Every technical source quotes house wiring in metres. Every shop in Pakistan sells it in coils. The conversion is metres ÷ 90, rounded up per size, because nobody cuts you a 1,793 m length — you buy 10 coils of 1.5 mm² and hold the offcut. That rounding is why the coil columns and the metre column do not reconcile exactly, and it is deliberate.

Confirm the coil length in writing before you order, from us or anyone else. A coil is conventionally 90 m and near enough 100 yards, but 45 m and 30 m coils exist, and a coil quoted in feet needs converting — 301 ft is 91.7 m, 1 m is 3.281 ft. The word "coil" is not a fixed quantity, and it is the number that quietly varies between suppliers.

Do not shave the list. The gap between 21 coils and 18 is three coils of copper and a circuit you cannot add later without opening plaster. On any plot size, the wire is the cheapest part of the wall it sits in.

These are planning quantities worked from a stated point count, run length and conductor count — not a certified load calculation and not a bill of quantities. Current capacities assume BS 7671 reference method C at 30°C; derate for conduit, bunching and summer ambient. Confirm the point schedule, circuit count and every cable size with a licensed electrician against your approved layout. Start with the cable size calculator for a single circuit, and the voltage drop calculator for anything over 20 m.

Work your own numbers

This table is a starting band. Three tools take it to your house.

Sizing one circuit rather than a whole house? The selection chart is on single-phase cable size, three-phase distribution is on 3 phase cable size, and the AC circuit is worked through end to end on cable for a 1.5 ton AC. What the labour and fittings add on top of the coil list is on cable installation cost.

Frequently asked

House wiring mein kitna wire lagta hai?
Plot ke hisab se: 3 marla par takreeban 11 coil, 5 marla par 21, 7 marla par 29, 10 marla par 43, 1 kanal par 71 aur 2 kanal par 125 coil — single storey, 90 m ka coil. Har figure 15% wastage ke saath hai aur point count par khari hai, plot area par nahi. Apne layout se points gin kar table se milaayen.
How many coils of wire does a 5 marla house need?
About 21 coils for a single storey: 10 coils of 1.5 mm², 9 of 2.5 mm² and 2 of 4 mm², which is roughly 1,793 m of conductor. That is 46 points on 11 circuits at a 12 m average run, with 15% wastage. A double-storey 5 marla comes to about 38 coils. The figures are taken from our 5 marla house wiring guide.
One coil kitne meter ka hota hai?
Every coil count on this page converts at 90 m, which is the standard coil of single-core house wire in Pakistan and near enough 100 yards. Coils are also sold at 45 m and 30 m, and some are quoted in feet — 301 ft is 91.7 m. The word "coil" is not a fixed quantity, so get the length in writing with the rate.
Why does the 10 mm² column stop after 5 marla?
Because 10 mm² on this table is not a house circuit — it is the service run from the meter to the distribution board, and it grows with the sanctioned load. At 5 kW and 7.5 kW the run is 10 mm². At 10 and 12 kW it steps to 16 mm², at 15 kW single phase to 25 mm², and a 25 kW three-phase 2 kanal takes 16 mm² four core.
Do these quantities include the earth wire and the meter cable?
The coil columns cover the circuits only. The 6 mm² earth conductor and the meter-to-DB service cable are listed separately as cut lengths, because you buy a measured length of each rather than a coil. Conduit, back boxes, switches, sockets, the distribution board and its MCBs are a separate purchase from an electrical store.
Double storey mein kitna extra wire lagega?
Roughly 80 to 90% more. The upper floor carries about 85% of the ground floor's points — no porch, no main entrance, no pump — and adds a riser to a second board. In coils: 3 marla goes 11 to 20, 5 marla 21 to 38, 7 marla 29 to 53, 10 marla 43 to 79, 1 kanal 71 to 131, 2 kanal 125 to 232.
How do I adjust this table to my own house?
Three inputs move it: your point count off the approved layout, the average run per point, and the conductors per run — 2.5 for lighting circuits, 3 for socket and appliance circuits. Multiply the three, add 15% for wastage, divide by 90 for coils. The method is worked circuit by circuit on our how much cable for a house page.
Kitna copper hota hai poori list mein?
Conductor copper only, before insulation: 18.40 kg on a 3 marla list, 36.40 kg on 5 marla, 50.40 kg on 7 marla, 76.00 kg on 10 marla, 123.20 kg on 1 kanal and 216.40 kg on 2 kanal. A 90 m coil holds area multiplied by 8.89 kg/km per mm² times 0.090 km — 1.20 kg on 1.5 mm², 2.00 kg on 2.5 mm², 3.20 kg on 4 mm² — so you can weigh a delivered coil and check it.

Send the coil list, get one factory rate

We draw the copper in Lahore and sell it at the day's rate — no dealer margin, and the line that made the coil answers the message. Send your plot size or your own coil list with your city: Punjab in 1–2 days, rest of Pakistan in 2–4.

Send the coil list and your city